Introduction
When planning a new kitchen or updating an existing one, installing worktops is one of the most significant steps in the process. Worktops are not only functional surfaces; they are central to the aesthetics, hygiene, and durability of your kitchen space. However, many homeowners and project managers underestimate the time required for a proper worktop installation. This can lead to rushed decisions, unrealistic expectations, and costly errors.
Understanding how long it truly takes to install a worktop—from choosing materials to the final fitting—can help you plan more effectively and avoid unnecessary delays. Whether you’re installing laminate, granite, quartz, or wood worktops, each material and installation scenario involves its own timeline, preparation requirements, and potential complications.
In this article, we break down the complete worktop installation timeline, discuss what to expect at each stage, highlight factors that may affect your schedule, and provide expert advice to help you plan with confidence.
Worktop Installation Timeline: How Long It Really Takes
1. Initial Consultation and Quotation (1–5 Days)
The first step in any worktop installation project is the consultation and quotation phase. During this stage, you’ll discuss your requirements with a supplier or kitchen designer, including your preferred materials, dimensions, cut-outs for sinks and hobs, and any finishing details such as edging and upstands.
- What to Expect:
The supplier may visit your home to take rough measurements or ask for kitchen layout drawings. Based on this information, they’ll prepare a cost estimate. - Typical Duration:
This step generally takes 1 to 5 days, depending on how quickly measurements are provided and how responsive the supplier is.
2. Final Measurement and Templating (1–3 Hours on-site, 2–7 Days for Processing)
Once the base cabinets have been installed and are level, accurate templating can begin. A technician visits your property to take precise digital or physical measurements. These are used to create a template that guides the fabrication of your bespoke worktop.
- What to Expect:
Templating can only happen once all cabinets are fixed, appliances are in place, and sinks or hobs have been selected. You must not move cabinetry after templating, as it would invalidate the template. - Typical Duration:
The on-site visit usually takes 1 to 3 hours. Fabrication based on the template typically takes 2 to 7 working days, depending on the material and supplier workload.
3. Fabrication (5–10 Working Days)
This is where your chosen worktop material is cut, polished, and prepared based on the templating data. Any necessary cut-outs, joins, drainage grooves, or special features are machined during this period.
- Material-Dependent Timelines:
- Laminate worktops: May be available off-the-shelf or with minimal fabrication time (2–4 days).
- Granite or quartz: Require professional fabrication and polishing (typically 5–10 working days).
- Solid wood: Generally quicker than stone but may still require cutting and sealing (3–7 days).
- What Can Delay This Stage:
Changes to the design after templating, material availability issues, or custom features can extend lead times.
4. Delivery and Installation (1 Day)
Once the worktops are fabricated, the installation team will arrive to fit them. This process includes carefully placing and securing the worktops, joining sections if needed, sealing edges, and installing sink and hob units.
- What to Expect:
- Cut-outs and joins are tested and adjusted on-site.
- Sealant and adhesives are applied.
- Final levelling and minor adjustments are made.
- Duration:
A standard installation usually takes one full day. Larger or more complex installations might require two days.
5. Post-Installation Curing, Sealing & Finishing Touches (1–3 Days)
After installation, the worktops need time to settle. Adhesives and sealants typically cure within 24 hours. If you’ve chosen natural stone or solid wood, additional sealing or oiling may be required to protect the surface and bring out its aesthetic quality.
- What to Expect:
- Avoid using the worktop for heavy tasks until curing is complete.
- The installer may return for final sealing or to check joins and finishes.
- Duration:
Allow an additional 1 to 3 days before fully using the space.
Summary Timeline
Stage | Duration |
Initial Consultation & Quotation | 1–5 Days |
Templating | 1–3 Hours (Visit) + 2–7 Days |
Fabrication | 5–10 Working Days |
Installation | 1 Day |
Curing & Finishing | 1–3 Days |
Total Estimated Time | 10–21 Days |
FAQs (Frequently Asked Questions)
Q1: Can I use my kitchen during the worktop installation process?
While base units may be in place, the kitchen is not fully functional until the worktop is installed. You’ll likely be without a sink or hob during this time, so it’s best to avoid regular kitchen use until installation and curing are complete.
Q2: What happens if my cabinets are not level or aligned during templating?
Accurate templating depends on stable and level base cabinets. If cabinets are misaligned, templating will be postponed until issues are corrected. Proceeding without addressing alignment can lead to costly fitting problems and voided warranties.
Q3: Can I speed up the installation process?
Some elements are fixed, such as fabrication time for stone worktops. However, you can streamline the process by having finalised plans, ensuring cabinetry is ready, and avoiding last-minute design changes.
Q4: Do all materials require the same installation time?
No. Laminate and wooden worktops are generally quicker to prepare and fit. Granite and quartz require templating and professional fabrication, which extends the timeline. Materials also differ in sealing and curing requirements.
Q5: What if the measurements are wrong or something doesn’t fit?
Errors in measurement or fabrication are rare but possible. Professional installers typically spot these issues during dry-fitting. If a mistake is discovered, a re-fabrication or modification may be needed, which could add several days to your timeline.
Q6: Should I arrange for plumbing and electrical work on the same day as worktop installation?
It’s better to schedule plumbing and electrical work for the day after installation. This allows adhesives to cure fully and reduces the risk of disturbing the newly installed surfaces. Coordinating with tradespeople in advance helps avoid delays.
Conclusion
Installing new worktops is a transformative step in any kitchen renovation, but it’s not something to rush. From initial consultation and templating to fabrication, fitting, and final sealing, each stage requires careful planning and professional execution.
On average, a complete worktop installation takes 10 to 21 days, depending on material choice, supplier timelines, and project complexity. Understanding this timeline enables you to plan your kitchen renovation more effectively and avoid common setbacks.
By working with experienced installers, preparing your space in advance, and allowing adequate time for curing and finishing, you’ll ensure that your new worktops are not only functional and attractive but also long-lasting and professionally fitted.